Project Update: 7/12/2019

Phase 2 of the project got underway July 10, 2019.  It  includes the closure of Franjo from SW 180th St to US 1 from a period of 100 days or until October 16, 2019

Unlike phase 1 - NO BUSINESSES WILL BE AFFECTED IN TERMS OF ACCESS

During this time, the following will occur: 

  • Set up Erosion Control
  • Clearing & Grubbing
  • Water & Sewer Installation
  • Drainage Installation
  • Undergrounding of Existing Overhead Utilities
  • Lighting & Irrigation
  • Roadway Subgrade Preparation
  • Concrete Curbs
  • Roadway Base Construction
  • 1st Lift of Asphalt
  • Concrete & Paver Sidewalk
  • Landscaping

Project Update: 6/04/2019

  • The first section of Franjo Road was opened to traffic yesterday. 
  • They are finalizing construction in this area (i.e. sidewalks, landscaping and lighting) 
  • There may be some occasional half closures (one bound at a time, either northbound or southbound Franjo) during off peak hours as they complete the construction. 
  • The infrastructure, namely conduits, etc., for FPL & AT&T undergrounding of overhead lines have been installed.
  • Proposed lighting conduits are in and most if not all, the light pole bases have been installed. 
  • Roadway reconstruction of subgrade, base and 1st lift of asphalt has been completed.

.