Miami-Dade County has now scheduled the timeline for the design, permitting and construction of "The People's Dock" in Palmetto Bay next to the Deering Estate, as well as the Mangrove Boardwalk. The issued timeline is as follows:
People's Dock:
Design start - beginning of May 2019 Design end - Aug 2019 - approx. 90 days
Permit start - Sept 2019 Permit ends - Feb 2020 - approx. 180 days
Bid start - Mar 2020 Bid ends - May 2020 - approx. 60 days
Construction start - June 2020 Construction ends - Dec 2020 - approx. 180 days
Agencies involved in review of Peoples Dock: RER(DERM), ACOE, FDEP, Village of Palmetto Bay
Mangrove Boardwalk:
Design start - beginning of May 2019 Design end - Sept 2019 - approx. 120 days
Permit start - Oct 2019 Permit ends - Oct 2020 - approx. 365 days
Bid start - Nov 2020 Bid ends - April 2021 - approx. 150 days
Construction start - May 2021 Construction ends - May 2022 - approx. 365 days
Agencies involved in review of the Mangrove Boardwalk: RER(DERM), ACOE, FDEP, Village of Palmetto Bay, Historical, Archeological, EEL