Construction of the four new traffic circles along Old Cutler Road is slated for the latter part of 2022. Since Old Cutler Road and the intersections where the traffic circles will be installed are all county-owned and managed roads, the project is under the full jurisdiction of Miami-Dade County. As updates become available to the Village, the information will be disseminated through the electronic newsletter and will be posted on this page in chronological order from newest to oldest.
For additional information regarding this project, please call 786-469-5365 or send an email to DTPWOutreach@miamidade.gov
Project Location: Old Cutler Rd from SW 68th Court to SW 64th Court
Project Start/End Dates:
Construction is scheduled to begin in September 2022 and is expected to be completed by September 2023*
*The start and end dates of this work may be significantly impacted by labor and material shortages associated with the ongoing Covid-19 pandemic, as well as by weather events characteristic of the hurricane season.
Project Scope: Reconstruct the existing Old Cutler Rd intersections and approaches at SW 136 ST and SW 67 Ave, including the installation of two (2) 4-lane roundabout at each of these intersections, roadway reconstruction, new sidewalks, new curb and gutters, drainage installation, street lighting, signalization removal, pavement markings and signage.
October 15, 2022 Update
Project Location: Old Cutler Road and SW 152nd Street Old Cutler Road and SW 184 Street
Project Start/End Dates: Construction is slated to begin this month at both intersections. The projects are expected to be completed by September 2023.
Project Scope: The work will include adding roundabouts, roadway reconstruction, new sidewalks, new curbs and gutters, drainage installation, adding street lighting, and paving.