News Flash

Traffic & Transit News

Posted on: July 3, 2019

Franjo Road Update

Phase II Construction Now Underway

Phase 2 of the Franjo Rd. reconstruction project is underway as of  July 10th, 2019.  It includes the closure of Franjo Rd. from SW 180th St to US 1 for a period of 100 days or until October 16, 2019

Unlike phase 1 - NO BUSINESSES WILL BE AFFECTED IN TERMS OF ACCESS

During this time, the following will occur: 

  • Set up Erosion Control
  • Clearing & Grubbing
  • Water & Sewer Installation
  • Drainage Installation
  • Undergrounding of Existing Overhead Utilities
  • Lighting & Irrigation
  • Roadway Subgrade Preparation
  • Concrete Curbs
  • Roadway Base Construction
  • 1st Lift of Asphalt
  • Concrete & Paver Sidewalk
  • Landscaping
.

Facebook Twitter Email

Other News in Traffic & Transit News

ibus app screenshot

IBUS Park & Ride App

Posted on: December 4, 2018

Florida Automated Vehicles Program

Posted on: June 18, 2019

Report Traffic Concerns Online

Posted on: August 27, 2018

Miami-Dade TPO Update

Posted on: June 18, 2019

About Roundabouts!

Posted on: April 4, 2019

Franjo Road Improvements Presentation

Posted on: January 30, 2019

TRAFFIC UPDATE: County Project

Posted on: April 3, 2019
franjo road notice of MOT

Upcoming Franjo Road Detour:

Posted on: January 30, 2019
traffic circle

Traffic Circle Rules: A Video

Posted on: October 24, 2018

SMART Plan Update

Posted on: February 6, 2017