FDOT 152 St Project Update

Posted on: June 15, 2018

FDOT's SW 152 St Project Update- June 15, 2018

Graphic-CoralReef_South_v1.6 (2)

US 1 Project Update- 6/15/18 
SR 5/US 1/S Dixie Hwy from north of SW 184 St to south of SW 168 St 

Project Identification Number: 428487-2-52-01

 

Project Start: January 16, 2018

Anticipated Completion Date: July 2018

 

Construction Activities:

  • Daytime utility/signalization work along northbound US 1 from SW 184 Street to SW 168 Street
  • Continue nighttime pavement milling and resurfacing activities at intersecting streets with US 1 from SW 184 Street to SW 168 Street
  • Nighttime striping of roadway and new crosswalks along project limits


Anticipated Lane Closures:

  • Friday, June 15 through Friday, June 22 - There will be alternating single lane closures on northbound US 1 from SW 184 Street to SW 168 Street between the hours of 9 a.m. and 3:30 p.m. and 9 p.m. and 5:30 a.mTemporary lane closures may occur at intersecting streets during night-time paving operations.


Please note that this schedule may change due to bad weather or other unforeseen conditions. 


Drivers are encouraged to call 511 before they travel or log on to www.fl511.com to get real-time traffic and lane closure information. FDOT would like to remind drivers that wearing a safety belt is the single most effective way to protect people and reduce fatalities in motor vehicle crashes. Please drive cautiously in construction zones.

 